4.06.475 Systemic Renovation - HVAC Unit vents in areas A and C are scheduled for replacement, they will be over 33 years old in 2023. Packaged Roof top units in areas B and C are scheduled for replacement, they will be over 35 years old in 2023. Provide new energy efficient HVAC systems based on latest codes and available technologies. Estimated Cost Initial Revised Cost Share Split $3,475,000 10/01/2013 07/09/2018 $2,550,000 State County $1,031,000 $2,444,000 County State $0 $0 $0 $1,031,000 $0 $0 $0 $0 $0 $0 $0 $2,444,000 $0 $0 $0 $0 $0 Total $0 $1,031,000 $2,444,000 $0 $0 $0 $0 Funding Prev. Approved 2024 2025 2026 2027 2028 2029 Out Years Total $1,031,000 $2,444,000 $3,475,000 Project Description 04 Fruitland Primary FY2024 WCBOE: Planning + Construction FY2024 CIP (FINAL 9/8/2022) 38