4.13.577 Systemic Renovation - Roofs As part of the Roof Refurbishment Program this school is due for a roof replacement. Replace roof - approximately 61,592 sf. Estimated Cost Initial Revised Cost Share Split $3,591,000 06/08/2020 06/27/2022 $3,046,000 State County $307,000 $3,284,000 County State $0 $0 $0 $0 $307,000 $0 $0 $0 $0 $0 $0 $3,284,000 $0 $0 $0 $0 $0 Total $0 $0 $3,591,000 $0 $0 $0 $0 Funding Prev. Approved 2024 2025 2026 2027 2028 2029 Out Years Total $307,000 $3,284,000 $3,591,000 Project Description 04 Fruitland Primary FY2024 WCBOE: Planning + Construction FY2024 CIP (FINAL 9/8/2022) 41