FY 2026 Capital Improvement Plan & Budget - County

49.13.629 Systemic Renovation - Roofs As part of the Roof Refurbishment Program this school is due for a roof replacement. Replace existing roof - 104,000 sf. Estimated Cost Initial Revised Cost Share Split $8,743,000 07/13/2023 01/01/1900 $7,093,000 State County $1,545,000 $7,198,000 County State $0 $0 $0 $0 $0 $1,545,000 $0 $0 $0 $0 $0 $0 $7,198,000 $0 $0 $0 $0 Total $0 $0 $0 $8,743,000 $0 $0 $0 Funding Prev. Approved 2026 2027 2028 2029 2030 2031 Out Years Total $1,545,000 $7,198,000 $8,743,000 Project Description 49 Salisbury Middle School FY2026 114 WCPS: Planning + Construction FY 2026 CIP (FINAL 9.4.2024)