FY 2026 Capital Improvement Plan & Budget - County

45.11.642 Site Acquisition - Studies / Planning The existing Wicomico Middle School is located on a 16-acre site with inadequate acreage to meet the programmatic needs of current and future middle school curriculum including adequate building square footage, recreation/sports fields, and circulation. These funds would allow for the acquisition of property and planning efforts to support a Wicomico Middle School replacement project (CIP project 45.6.635). Estimated Cost Initial Revised Cost Share Split $0 07/25/2024 $3,000,000 State County $3,000,000 $0 County State $0 $0 $3,000,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 Total $3,000,000 $0 $0 $0 $0 $0 $0 Funding Prev. Approved 2026 2027 2028 2029 2030 2031 Out Years Total $3,000,000 $0 $3,000,000 Project Description 45 Wicomico Middle FY2026 99 WCPS: Planning + Construction FY 2026 CIP (FINAL 9.4.2024)

RkJQdWJsaXNoZXIy MTI2NzY2OQ==