FY 2026 Educational Facilities Master Plan

LEA: DATE: SCHOOL: Pemberton Elementary School S.R.C. 523 ACTUAL YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 YEAR 6 YEAR 7 YEAR 8 YEAR 9 YEAR 10 B.D.C. 575 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 Y-3 15 Pre-K 73 85 85 85 85 85 85 85 85 85 85 KINDERGARTEN 63 84 71 79 78 79 77 76 76 76 76 1st 81 69 82 69 77 76 77 75 74 74 74 2nd 80 87 67 79 67 75 72 75 73 72 72 3rd 66 79 76 59 70 59 66 63 66 64 63 4th 76 72 77 74 57 68 57 63 61 63 62 5th 67 91 77 82 79 61 68 59 66 63 66 6th 7th 8th 9th 10th 11th 12th TOTAL w/out Pre-K 433 482 450 442 428 418 416 412 416 413 413 TOTAL w/ Pre-K 521 567 535 527 513 503 501 497 501 498 498 TOTAL w/out Pre-K is the sum of K-12 TOTAL w/ Pre-K is the sum of Pre-K-12 (Y-3 is not included) FTE ENROLLMENT PROJECTIONS BY GRADE ENROLLMENTS AS OF SEPTEMBER 30TH Wicomico County September 30, 2024 11 4/11/2025 FINAL Facilities | Planning + Construction 243