Wicomico County Public Schools | EFMP FY2026 LEA: DATE: SCHOOL: S.R.C. 362 ACTUAL YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 YEAR 6 YEAR 7 YEAR 8 YEAR 9 YEAR 10 B.D.C. 361 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 Y-3 Pre-K 36 34 34 34 34 34 34 34 34 34 34 KINDERGARTEN 64 77 68 76 75 76 74 73 73 73 73 1st 72 78 75 66 74 73 74 72 71 71 71 2nd 72 84 81 78 69 77 73 74 72 71 71 3rd 67 85 89 86 83 73 77 73 74 72 71 4th 5th 6th 7th 8th 9th 10th 11th 12th TOTAL w/out Pre-K 275 324 313 306 300 298 298 292 290 287 286 TOTAL w/ Pre-K 311 358 347 340 334 332 332 326 324 321 320 TOTAL w/out Pre-K is the sum of K-12 TOTAL w/ Pre-K is the sum of Pre-K-12 (Y-3 is not included) FTE ENROLLMENT PROJECTIONS BY GRADE ENROLLMENTS AS OF SEPTEMBER 30TH Wicomico County September 30, 2024 Willards Elementary School 16 4/11/2025 FINAL Facilities | Planning + Construction 248