FY 2027 Capital Improvement Plan & Budget - County

46.06.445 Systemic Renovation - Lighting Systems Lighting systems and ceilings have passed their useful life in areas A through I. Upgrades are needed in order to provide adequate lighting levels and additional operational efficiencies. Upgrade lighting fixtures and associated ceilings that have exceeded their useful lives. Project includes electrical service upgrades and branch wiring as required to accommodate new lighting. Estimated Cost Initial Revised Cost Share Split $8,979,000 10/01/2013 07/12/2023 $4,290,000 State County $685,000 $8,294,000 County State $0 $0 $685,000 $0 $0 $0 $0 $0 $0 $8,294,000 $0 $0 $0 $0 $0 $0 $0 Total $8,979,000 $0 $0 $0 $0 $0 $0 Funding Prev. Approved 2027 2028 2029 2030 2031 2032 Out Years Total $685,000 $8,294,000 $8,979,000 Fiscal Year County Requested State Requested County Deferred State Deferred County Approved State Approved Other 2026 $989,000 $7,990,000 $989,000 $7,990,000 $0 $0 $0 Funding History Project Description 46 Wicomico High School FY2027 WCPS: Planning + Construction FY 2027 CIP (FINAL 9.2.2025) 106

RkJQdWJsaXNoZXIy MzAyOTMwNA==