FY 2027 Capital Improvement Plan & Budget - County

5.13.578 Systemic Renovation - Plumbing - Boiler The existing boiler has reached the end of its useful life based on age. Replace existing gas/oil fired boiler for hot water. Estimated Cost Initial Revised Cost Share Split $503,000 06/08/2020 07/09/2025 $479,000 State County $503,000 $0 County State $0 $0 $503,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 Total $503,000 $0 $0 $0 $0 $0 $0 Funding Prev. Approved 2027 2028 2029 2030 2031 2032 Out Years Total $503,000 $0 $503,000 Project Description 05 Fruitland Intermediate FY2027 WCPS: Planning + Construction FY 2027 CIP (FINAL 9.2.2025) 45