19.13.633 Systemic Renovation - Roofs Portions of the building roof is reaching the end of its useful life and needs replaced / refurbished. Replace / refurbish Built Up Roof (BUR) portion - 13,975 sf. Estimated Cost Initial Revised Cost Share Split $0 07/17/2023 $954,000 State County $954,000 $0 County State $0 $0 $0 $0 $0 $0 $954,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 Total $0 $0 $0 $0 $954,000 $0 $0 Funding Prev. Approved 2027 2028 2029 2030 2031 2032 Out Years Total $954,000 $0 $954,000 Project Description 19 Willards Elementary FY2027 WCPS: Planning + Construction FY 2027 CIP (FINAL 9.2.2025) 81
RkJQdWJsaXNoZXIy MzAyOTMwNA==