FY 2027 Educational Facilities Master Plan

Wicomico County Public Schools | EFMP FY2027 LEA: DATE: SCHOOL: Northwestern Elementary School S.R.C. 251 ACTUAL YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 YEAR 6 YEAR 7 YEAR 8 YEAR 9 YEAR 10 B.D.C. 274 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 Y-3 Pre-K 22 40 40 40 40 40 40 40 40 40 40 KINDERGARTEN 34 41 44 45 44 45 45 44 44 44 44 1st 40 31 37 40 41 40 41 41 40 40 40 2nd 48 37 29 35 37 38 37 38 38 37 37 3rd 33 38 29 23 27 29 30 29 30 30 29 4th 41 30 34 27 21 25 27 27 27 27 27 5th 49 38 28 31 24 19 23 24 25 24 25 6th 7th 8th 9th 10th 11th 12th TOTAL w/out Pre-K 245 214 201 200 194 196 202 204 203 203 202 TOTAL w/ Pre-K 267 254 241 240 234 236 242 244 243 243 242 TOTAL w/out Pre-K is the sum of K-12 TOTAL w/ Pre-K is the sum of Pre-K-12 (Y-3 is not included) FTE ENROLLMENT PROJECTIONS BY GRADE ENROLLMENTS AS OF SEPTEMBER 30TH Wicomico County September 30, 2025 10 4/16/2026 FINAL Facilities | Planning + Construction 252

RkJQdWJsaXNoZXIy MzAyOTMwNA==